Answer:
The answer is letter A.
Step-by-step explanation:
This represents the path of tasks that will take the longest to complete.
Because the critical path is the path of tasks that will take longer to complete. If the director experiences any delays in the completion of these tasks, the entire acitvity will be delayed.