Answer:
C. 30
Step-by-step explanation:
If the first machine processes 100 units in 5 hours,
Number of units in 1 hour = 100/5
= 20 Units
In 2 hours, this machine would process
= 2 × 20
= 40 Units
Therefore where there are 100 units to be processed in 2 hours, the first machine would process 40 units in the given time
The new machine would have to process the remaining
Number of units to be processed by new machine
= 100 - 40
= 60 Units
If the machine is to process 60 units in 2 hours, constant rate, in units per hour, of the new machine
= 60/2
= 30 units per hour