Dallas Company uses a job order costing system. The company's executives estimated that direct labor would be $3,360,000 (240,000 hours at $14/hour) and that factory overhead would be $1,540,000 for the current period. At the end of the period, the records show that there had been 220,000 hours of direct labor and $1,240,000 of actual overhead costs. Using direct labor hours as a base, what was the predetermined overhead rate? (Round your answer to two decimal places.)

A) $5.17 per direct labor hour.
B) $7.00 per direct labor hour.
C) $6.42 per direct labor hour.
D) $5.84 per direct labor hour.
E) $6.25 per direct labor hour.

User Lionscribe
by
8.3k points

1 Answer

4 votes

Answer:

Option (C) is correct.

Step-by-step explanation:

Given that,

Estimated overhead cost = $1,540,000

Estimated direct labors (in dollars) = $3,360,000

Estimated direct labor hours = 240,000

Actual overhead cost = $1,240,000

Predetermined overhead rate:

= Estimated overhead cost ÷ Estimated direct labor hours

= $1,540,000 ÷ 240,000

= $6.42 per direct labor hour