Answer:
- For company B: Workers: 131; Supervisor: 14; Line Manager: 2; Senior Manager: 1; COO: 1
- For company C: Workers: 26; Supervisor: 6; Line Manager: 2; Senior Manager: 1; COO: 1
- For combined Company: Workers: 157; Supervisor: 16; Line Manager: 2; Senior Manager: 1; COO: 1
Step-by-step explanation:
- For company B:
+ Number of workers needed = Number of person-hours needed/ total number of working hour in a year = 250,000/ (240 x 8) = 131 workers.
=> Number of supervisor needed = 14; Number of Line manager needed = 2; Number of Senior needed = 1; Number of COO needed = 1 ( that is 1 upper management level for every 10 lower level).
- For Company C:
+ Number of workers needed = Number of person-hours needed/ total number of working hour in a year = 50,000/ (240 x 8) = 26 workers.
=> Number of supervisor needed: 6; Number of Line manager needed = 1; Number of Senior needed = 1; Number of COO needed = 1 ( that is 1 upper management level for every 5 lower level).
- For the combined firm:
+ Total number of workers: 131+ 26 = 157 workers
=> Number of supervisor needed = 16; Number of Line manager needed = 2; Number of Senior needed = 1; Number of COO needed = 1 ( that is 1 upper management level for every 10 lower level).