The project manager building a new underwater dolphin exhibit at Chicago's Shedd Aquarium is reviewing the chronological sequence of activities that must be completed on the project and the estimated time of completion of each activity. He is employing the

A. Gantt chart.
B. total quality management process.
C. PERT technique.
D. lean manufacturing process.

User Jbielick
by
5.5k points

1 Answer

6 votes

Answer: C. PERT technique

Step-by-step explanation:

Project Evaluation and Review Technique is a technique used by project managers to control an ongoing project.

It is also used to analyse and followup project activities in order to meet up with the deadline for the project.

PERT is mainly used to analyse and control a project. Its main objective is to reduce project cost as well as manage the allotted time for the completion of the project.