Department C had direct materials EUP cost of $4.00 and conversion EUP cost of $2.50. If the department had 38,000 units completed and transferred to the next department, their cost of units completed for direct materials is $

User Karfus
by
7.1k points

1 Answer

4 votes

Answer:

Their cost of units completed for direct materials is $1,52,000.

Step-by-step explanation:

Cost of units completed for direct materials

= Units completed and transferred *Direct material EUP cost

= 38,000 *$4.00

= $1,52,000

Therefore, Their cost of units completed for direct materials is $1,52,000.