Zhang Industries budgets production of 290 units in June and 300 units in July. Each unit requires 1.5 hours of direct labor. The direct labor rate is $13.80 per hour. The indirect labor rate is $20.80 per hour. Compute the budgeted direct labor cost for July.

1 Answer

2 votes

Answer:

otal labor cost= $6,003

Step-by-step explanation:

Giving the following information:

Zhang Industries budgets production of 290 units in June and 300 units in July. Each unit requires 1.5 hours of direct labor. The direct labor rate is $13.80 per hour. The indirect labor rate is $20.80 per hour.

Total labor cost= (290*1.5)*13.8= $6,003