If it takes a person to dig a garden in 6 days and another person 2 days how many days would it take for them to finish together

User Hyojin
by
4.9k points

1 Answer

5 votes

Answer:

4 Days

Explanation:

Because, The 6 day person would slow down the 2 day person to 4 days :)