159k views
2 votes
A supermarket manager notices that there are 20 customers at the checkouts and also knows that arrivals to the checkout at that time of day are at a rate of about two per minute. About how long are customers spending in the checkout process (queueing and being served) on average?

1 Answer

1 vote

Answer:

On an average customers are spending 10 minutes in the queue.

Step-by-step explanation:

Please see attachment

A supermarket manager notices that there are 20 customers at the checkouts and also-example-1
User AdelaN
by
5.2k points