46.6k views
5 votes
Earned value measurement systems must be capable of: Select one: a. Measuring resources consumed b. Measuring status and accomplishment c. Provide a basis for diagnosis and replanning d. All of the above

User Bniwredyc
by
5.4k points

1 Answer

5 votes

Answer:

The answer is D, all of the above

Step-by-step explanation:

Earned Value Measurement helps project managers to properly track and measure project performance. It is a systematic project management process used to find discrepancy and variances in projects based on the comparison of worked performed, resource utilized and work planned.

User Kwolf
by
5.5k points