67.0k views
3 votes
Better Houses Inc. has been contracted to build an addition on the Joyners' house. It built half of the addition and then unexpectedly announced that it wasn't going to finish the job. Better Houses decision to stop the job is called a/an A. substantial performance. B. repudiation of contract C. abandonment of contractual obligations. D. constructive breach of contract

1 Answer

6 votes

Answer: Option C

Explanation: In simple words, abandonment of contractual obligations refers to the situation when one party fails or deny to preform an obligation that was agreed to be performed under a contract.

In such cases the party abandoning the contract also looses the right to earn the agreed consideration. In the given case, Better houses refuses to build the house in middle of the construction.

Hence we can conclude that the given case depicts abandonment of contractual obligations.

User Ulrich Dangel
by
5.4k points