Machine A can complete a certain job in x hours. Machine B can complete the same job in y hours. If A and B work together at their respective rates to complete the job, which of the following represents the fraction of the job that B will not have to complete because of A's help?

A) (x – y)/(x + y)
B) x/(y – x)
C) (x + y)/(xy)
D) y/(x – y)
E) y/(x + y)

User Avon
by
9.0k points

1 Answer

5 votes

Answer:

E) y / ( x + y )

Explanation:

Machine A need x hours to do the job

Then in one our machine A do 1/x of the job

Machine B need y hours to do the job

Then in one hour machine B do 1/y of the job

Then the two machines working together in one our time will make:

1/x + 1/ y = ( y + x ) xy

And the fraction of the job B does not need to do, since it was done by machine A is

( 1/x ) / (y + x ) / xy = y / ( x + y )

User Ankish Bansal
by
7.7k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories