Answer:
$0.51
Step-by-step explanation:
The computation of the predetermined overhead rate. The formula is shown below:
Predetermined overhead rate = (Total estimated manufacturing overhead) ÷ (estimated direct labor-hours)
where,
Estimated overhead costs for the year is $25,000
And, the estimated direct labor cost would be
For Totes
= $52 × 500 units
= $26,000
For Satchels
= $65 × 360 units
= $23,400
So, the total direct labor cost would be
= $26,000 + $23,400
= $49,400
Now put these values to the above formula
So, the value would equal to
= $25,000 ÷ 49,400
= $0.51