Answer:
$345,700
Step-by-step explanation:
Cost of goods manufactured:
= Material used in product + Depreciation on plant + Labor costs of assembly-line workers + Factory supplies used + Property taxes on plant + Work in process inventory(at Jan 1) - Work in process inventory(at Dec 1)
= $126,100 + 70,700 + 111,900 + 24,000 + 16,500 + $12,000 - $15,500
= $345,700