The following labor standards have been established for a particular product: Standard labor-hours per unit of output 8.6 hours Standard labor rate $ 15.50 per hour The following data pertain to operations concerning the product for the last month: Actual hours worked 8,500 hours Actual total labor cost $ 129,200 Actual output 840 unitsWhat is the labor rate variance for the month? F or UWhat is the labor efficiency varaiance for the month? F or U

User Wright
by
6.3k points

1 Answer

3 votes

Answer:

Instructions are listed below.

Step-by-step explanation:

Giving the following information:

Standard labor-hours per unit of output 8.6 hours Standard labor rate $ 15.50 per hour The following data pertain to operations concerning the product for the last month: Actual hours worked 8,500 hours Actual total labor cost $ 129,200 Actual output 840 units

Actual rate= 129,200/8,500= 15.2

Direct labor price variance= (SR - AR)*AQ

Direct labor price variance= (15.5 - 15.2)*8,500= $2,550 favorable

Direct labor efficiency variance= (SQ - AQ)*standard rate

Direct labor efficiency variance= (7,224 - 8,500)*15.5= $19,778 unfavorable