Two companies working together can clear a parcel of land in 30 hours. Working alone, it would take Company A 3 hours longer to clear the land than it would Company B. How long would it take Company B to clear the parcel of land alone? (Round your answer to the nearest tenth.)

User Kamil W
by
6.3k points

1 Answer

3 votes
I think it would take Company B 15hrs to clear the land, and Company A would take 18hrs.