Granite Company purchased a machine costing $133,000, terms 2/10, n/30. The machine was shipped FOB shipping point and freight charges were $3,300. The machine requires special mounting and wiring connections costing $11,300. When installing the machine, $2,800 in damages occurred. Compute the cost recorded for this machine assuming Granite paid within the discount period.

User Jelford
by
6.0k points

1 Answer

5 votes

Answer:

$144,940

Step-by-step explanation:

machine costing = $133,000

freight charges = $3,300

special mounting and wiring connections costing = $11,300

Discount rate = 2%

Compute the machine cost as given below:

Machine cost:

= Purchase price × (1 - Discount rate) + Freight charges + Special mounting and wiring connection cost

= 133,000 × (1 - 2%) + $3,300 + $11,300

= $144,940