Answer:
A) exceeds a pre-determined target average accounting return.
Step-by-step explanation:
accounting rate of return/ ARR is used to evaluate capital budgeting decisions and it ignores time value of money.
if ARR is equal to or greater than the required rate of return, then the project should be accepted.