When it is necessary to reduce project duration and resources are constrained, which of the following is NOT a reasonable option?

Select one:
a. Compromise quality
b. Establishing a core project team
c. Reduce project scope
d. Fast-tracking
e. Critical-chain project management

User Terrabl
by
7.0k points

1 Answer

4 votes

Answer:

B. Establishing a core project team.

Step-by-step explanation:

Project managers can speed up the completion date by establishing a core project team only if they have the additional resources and the additional funds.