Why is it necessary to have a time-phased budget baseline? Select one: a. It allows proper resource allocation b. It reduces schedule slippage when scheduling multiproject resources c. It reduces fluctuations in cash flow during the project d. It shows how much work was accomplished for the money spent e. It is not necessary to have a time-phased budget baseline

User Smcameron
by
8.2k points

1 Answer

3 votes

Answer:D. It shows how much work was accomplished for the money spent

Step-by-step explanation:

Time phased budget is an approved plan of how much work should be accomplished at stated time on the money spent on a project