75.1k views
4 votes
A production manager is evaluated based on the quantity of direct materials used in production. If the production line actually uses materials to produce 50,000 units when the master budget shows materials needed for 44,000 units, the manager's evaluation should be based on a flexible budget. True or False

2.) Which of the following remains the same when comparing a flexible budget to a master budget?
A. Total sales.
B. Net income.
C. Total variable costs.
D. Total fixed costs.

1 Answer

3 votes

Answer:

1) True

2) D. Total fixed costs

Step-by-step explanation:

1) The manager's evaluation should be based on a flexible budget, so the statement is true.

The standard quantity of direct materials used should be based on actual production for a correct variance analysis.

2 ) Total fixed costs remains the same when comparing a flexible budget to a master budget.

Total fixed costs do not change in total within relevant range of production.

User Allenylzhou
by
6.5k points