2018, the westgate construction company entered into a contract to construct a road for santa clara county for $10,000,000. the road was completed in 2020. information related to the contract is as follows: 2018 2019 2020 cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 estimated costs to complete as of year-end 5,256,000 2,628,000 0 billings during the year 2,170,000 2,502,000 5,328,000 cash collections during the year 1,885,000 2,600,000 5,515,000 westgate recognizes revenue over time according to percentage of completion.

1 Answer

5 votes

Answer:

2018: 28% 2,800,000

2019: 22% 2,200,000

2020: 50% 5,000,000

Step-by-step explanation:

2018 revenue

total cost:

2,044,000 + 5,256,000 = 7,300,000

percentage of completion: 2,044,000/7,300,000 = 28%

revenue recognition: 10,000,000 x 28% = 2,800,000

2019 revenue

cost: 2,628,000 + 2,628,000 = 5,256,000

percentage of completion: 2,628,000 / 5,256,000 = 50%

revenue recognition: 10,000,000 x (50% - 28%) = 2,200,000

2020 revenue

as the company's finished the cosntruction it recognzie the entire amount left

10,000,000 - 2,800,000 - 2,200,000 = 5,000,000