Answer:
D. Timeline of the project may change
Step-by-step explanation:
In a project, activities tend to have a dependency relationship on one another. Delay in one activity may result in project schedule slippage if it happens to be on the critical path. As a result, when a project manager receives a communication about one of the tasks getting delayed- namely, the report being late , it implies that the timeline of the project may possibly change.