Teatro Restoration, Inc., begins renovating an old theater for Urban Edge Productions, but after three months Teatro demands an extra $250,000. Urban Edge agrees to pay. Refer to Fact Pattern 13–4. ​If Teatro says it is asking for the extra $250,000 because ordinary business expenses have increased, the agreement is:

1 Answer

4 votes

Answer: Cost plus contract

Step-by-step explanation:

A contract in which the contractor is reimbursed on allowable expenses and paid an agreed percentage of the total allowable expenses.