Answer:
Activity variance = $2485 F
Step-by-step explanation:
given data
wages and salaries = $1,540 per month
per birth = $497
activity = 112 births
actual wages and salaries = $56,850
to find out
activity variance for wages and salaries in March
solution
we get here Wages and salaries in Planning budget is here express as
Wages and salaries in Planning budget = 1540 + (497 × 112)
Wages and salaries in Planning budget = $57204 .....................1
and
Wages and salaries in Flexible budget will be here
Wages and salaries in Flexible budget = 1540 + (497 × 107)
Wages and salaries in Flexible budget = $54719 .......................2
so Activity variance will be difference of equation 1 and 2
Activity variance = $57204 - $54719
Activity variance = $2485 F