Answer:
$80,000
Step-by-step explanation:
For computing the total overhead cost, first we have to compute the plant wide rate which is shown below:
= (Machine hours cost + setup cost + received order cost + packing order cost) ÷ (Total machine hours)
= ($70,000 + $50,000 + $10,000 + $30,000) ÷ (24,000 machine hours)
= $160,000 ÷ 24,000 machine hours
=$6.67
Now the total overhead cost equals to
= Machine hours of 35 mm × plant wide rate
= 12,000 machine hours × $6.67
= $80,000