Answer:
The number of days required for 8 men working to complete 4 copies of the books is 6 days
Explanation:
Given As
The number of men (M1) = 10
The number of working days (D1) = 6 days
The work done (W1) = 5 copies
Again,
The number of men (M2) = 8
The number of working days (D2) = D2 days
The work done (W2) = 4 copies
∵
= constant
So ,

or,

Or,
=

Or, D2 =

∴ D2 = 6 days
Hence The number of days required for 8 men working to complete 4 copies of the books is 6 days Answer