Answer:
Total overhead = = $7,500
so here correct option is E. $7,500
Step-by-step explanation:
given data
production = 1,000 units
direct labor = ¼ hour @ $24 per hour
variable overhead = 75 % of direct labor
fixed overhead = $3,000
to find out
total amount of overhead
solution
we first find Direct labor that is
Direct labor = ¼ × 24
Direct labor = $6
so
Total overhead will be here
Total overhead = Variable overhead + Fixed overhead .................1
now put here value we get
Total overhead = ($6 × 75% ) × 1,000 + $3,000
so
Total overhead = = $7,500
so here correct option is E. $7,500