a company has established 5 pounds of material j at $2 per pound as the standard for the material in its product z. the company has just produced 1,000 units of this product, using 5,200 pounds of material j that cost $9,880. the direct materials quantity variance is:

1 Answer

1 vote

Answer:

direct materials quantity variance = 520 Favourable

Step-by-step explanation:

given data

material = $2 per pound

produced = 1,000 units

Actual Quantity of Material = 5200

cost = $9,880

to find out

direct materials quantity variance

solution

we get here Material Price Variance that is express as

direct materials quantity variance = ( Standard Cost - Actual Cost) Actual Quantity of Material .......................1

put here value we get

direct materials quantity variance = 2-
(9880)/(5200) × 5200

direct materials quantity variance = 520 Favourable