Answer:
the order will likely be rejected
Step-by-step explanation:
• Maximum theoretical capacity, nominal or design capacity. It is the one defined when a new (industrial) installation is planned where it is expected to achieve a certain ideal production when the plant is effectively in operation, it is the capacity that we will obtain if we work 365 days a year for 24 hours. of the day, it is a theoretical value never attainable. If we have entrusted the assembly of the plant to third parties, I think it is necessary that its suppliers define said Maximum Theoretical Capacity, so we should demand that both agree.
• Maximum Practical Capacity. It is the industrial capacity where it is expected to achieve a certain production when the plant is effectively in operation.
• Effective or Demonstrated Capacity. It is the one obtained in normal operating conditions with the normal calendar and usual shifts, with a state of maintenance of the process within the usual. It is a capacity that can be sustained for continuous (long) periods of time.
Already described the definition of maximum capacity there is no reason why we should accept a single order in disadvantageous conditions, since it is assumed that if you are working at maximum capacity it is because you can place the generated product on the market.