The court would most likely rule in Eiln's favor
Step-by-step explanation:
Even though its up to each court to decide the veredict, the decison will rest on whether the inclusion of the contract clause “to be used for daughter’s wedding reception on May 2nd created an express condition rendering the time of performance vital to the purpose of the contract.
If the time for performance is not of the essence, a reasonale time for performance is allowed. A late performance in such a case does not constitute material breach, but the party rendering late performance is liable for damages caused by the delay. In this case, although May 2nd would ordinarily be reasonable time for performance, the inclusion of the phrase giving the use of the wine and date of the reception would render the time vital to performance and would require strict compliance. Grapes & Vine’s failure to deliver on May 1 is a material breach releasing Elin from any liability under the contract.