Answer:
$3,600 unfavorable
Step-by-step explanation:
Given:
Standard material price = $9 per square foot
Actual material price = $9.2 per square foot
Standard material = 3 square feet
Standard material allowed = 1,000 × 3 = 3,000 square feet
Actual material used = 3,400 square feet
Direct material quantity variance = (Standard material allowed - Actual) × Standard price per unit
= (3000 - 3400) × 9
= $3,600 unfavorable
Actual material used is more than standard material allowed, so variance is unfavorable.