The items discussed in a(n) _____ include reflections on whether project goals were met, whether the project was successful or not, the causes of variances on the project, the reasoning behind corrective actions chosen, the use of different project management tools and techniques, and personal words of wisdom based on team members’ experiences.

User Inky
by
5.8k points

1 Answer

5 votes

Answer:

Lessons-learned report.

Step-by-step explanation:

The main purpose of the "lessons learned report" is to provide future project teams with information that can increase effectiveness and efficiency and to build on the experience that has been earned by each project, successful or not. The name itself is key to understanding that the main purpose is to learn what can be improved, what can be avoided, what can be better.