Answer:
c. 0.9768
Step-by-step explanation:
Lead time
Safety stock 500
Standard deviation 145
Safety stock = z * Standard deviation *
500 = z * 145*
500 = z * 251.14
Z = 1.990863
Therefore, for this Z value, we obtain the option c. 0.9768