3.4k views
0 votes
Project A has an initial cost of $80,000 and provides cash inflows of $34,000 a year for three years. Project B has an initial cost of $80,000 and produces a cash inflow of $114,000 in year 3. The projects are mutually exclusive. Which project(s) should you accept if the discount rate is 11.7 percent? What if the discount rate is 13.5 percent?

(A) Accept A as it always has the higher NPV.
(B) Accept B as it always has the higher NPV.
(C) Accept B at .11.7 percent and A at 13.5 percent.
(D) Accept A at 11.7 percent and B at 13.5 percent.
(E) Accept A at 11.7 percent and neither at 13.5 percent.

User Jason Cust
by
5.2k points

1 Answer

3 votes

Answer: A

Explanation: Using a financial calculator to solve the problem :

For project A with a discount rate of 11.7%

Outlay = 80,000

CF for year 1 = 34000

CF for year 2 = 34000

CF for year 3 = 34000

I = 11.7 %

NPV = 2085

For project A with a discount rate of 13.5%

Outlay = 80,000

CF for year 1 = 34000

CF for year 2 = 34000

CF for year 3 = 34000

I = 13.5%

NPV = -397.5

For project B with a discount rate of 11.7%

Outlay = 80,000

CF for year 1 = 0

CF for year 2 = 0

CF for year 3 = 114,000

NPV = 1798

For project B with a discount rate of 13.5%

Outlay = 80,000

CF for year 1 = 0

CF for year 2 = 0

CF for year 3 = 114,000

NPV = -2,032

from the above calculations, project A has a better NPV when discount rate is 11.7% and 13.5%

Project A has an initial cost of $80,000 and provides cash inflows of $34,000 a year-example-1
User Adam Lassek
by
5.4k points