If a job consists of a batch of identical​ units, how can managers find the unit​ cost? A. By tracing direct labor to each unit B. By multiplying the total job cost by the number of units in the job C. By tracing direct materials to each unit D. By dividing the total job cost by the number of units in the job

User Ijung
by
8.1k points

1 Answer

3 votes

Answer: A Manager can find the unit cost by:

C. By tracing direct materials to each unit.

Explanation: When each material can be traced directly to their respective unit, it would be possible and easier to find the unit cost of each specific job.