35.3k views
4 votes
it takes 36 minutes for 7 people to paint 4 walls.How many minutes does it take 9 people to paint 7 walls

1 Answer

3 votes

Answer:

The time required by 9 people to paint 7 walls is 49 minutes

Explanation:

Given as :

The number of people (p1) = 7

The work done by them (w1) = 4

The time taken (T1) = 36 minutes

Again :

The number of people (p2) = 9

The work done by them (w2) = 7

Let the time Time taken (T2) = T2

So, we know as :


(MEN * TIME)/(WORK) = Constant

SO,
(P1 * T1)/(W1) =
(P2 * T2)/(W2)

Or,
(7 * 36 min)/(4) =
(9 * T2)/(7)

Or,
(252)/(4) =
(9 T2)/(7)

Or ,
(252 * 7)/(9* 4) = T2

∴ T2 = 49 minutes

Hence The time required by 9 people to paint 7 walls is 49 minutes Answer