Which of the following elements is NOT used in a decision tree analysis for selection of the number of suppliers under​ risk? A. the financial loss incurred in a supply cycle if all suppliers were disrupted B. the probability of a​ "super-event" that would disrupt all suppliers simultaneously C. the probability of a​ "unique-event" that would disrupt all suppliers simulataneously D. the marginal cost of managing a supplier.

User Roxrook
by
8.1k points

1 Answer

1 vote

Answer: d) that marginal cost of managing a supplier