Answer:
total amount of overhead applied = $265680
Step-by-step explanation:
given data
Actual direct labor hours = 8200
overhead rate = 32.40 per DLH
to find out
total amount of overhead applied
solution
we will apply here formula for total amount of overhead applied that is
total amount of overhead applied = Actual direct labor hours × overhead rate ..................1
put here value in equation 1 we get
total amount of overhead applied = 8200 × $32.40
total amount of overhead applied = $265680