93.3k views
1 vote
Indiana Co. began a construction project in 2018 with a contract price of $150 million to be received when the project is completed in 2020. During 2018, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Indiana A) Recognized no gross profit or loss on the project in 2018. B) Recognized $6 million loss on the project in 2018. C) Recognized $9 million gross profit on the project in 2018. D) Recognized $36 million loss on the project in 2018.

User Munleashed
by
5.3k points

1 Answer

4 votes

Answer:

C) Recognized $9 million gross profit on the project in 2018.

Step-by-step explanation:

contract: 150,000,000 revenue

incurred cost: 36,000,000

addition cost: 84,000,000

total cost: 120,000,000

percentage of completion: 36,000,000/120,000,000 = 0.3

revenue: 150,000,000 x 30% = 45,000,000

gross profit:

revenue 45,000,000

cost: (36,000,000)

gross profit: 9,000,000

User BobDroid
by
6.1k points