Answer:
Project A is better than Project B because it has a bigger net present value.
Step-by-step explanation:
Giving the following information:
Project A:
Io= -52,000
1= 25,300
2= 37,100
3= 22,000
Project B:
Io= -52,000
1= 43,600
2= 19,800
3= 10,400
The required rate of return is 14.2 percent for Project A and 13.9 percent for Project B.
We need to calculate the Net Present Value of each project.
NPV= -Io + ∑[Cf/(1+i)^n]
Project A:
NPV= - 52,000 + (25,300/1.142) + (37100/1.142^2) + (22000/1.142^3) = 13,372.95
Project B:
NPV= 8,579.62
Project A is better than Project B because it has a bigger net present value.