Answer:
machine hours= 9760 hours
Step-by-step explanation:
Giving the following information:
Rager Corporation applies manufacturing overhead based on machine-hours.
The company based its predetermined overhead rate on the total estimated overhead of $100,040. The company's predetermined overhead rate for the year was $10.25 per machine-hour.
Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
10.25= 100,040/ total amount of allocation base
machine hours= 100,040/10.25= 9760 hours