2A-1 Electrical Company charges $45 for a service call. After the first hour (h), there is a $25 hourly charge. Materials (m) for the

job are an additional cost. Which equation could be used to find the cost (C) to the customer if the job takes a total of h hours?
C=45+25h+m
C=45+25(h + m)
©
C=45+ 25( - 1) +m
C=45 + 25(h - 1)

2 Answers

2 votes

The answer would be - C=45+25h=m

For the first hour, the electrical company charges $45 dollars. For the hours after, he charges $25 dollars. Since we do not know how many hours he worked, we put $25h in the expression. Then there is materials, which we also do not know what it cost. Therefore, the expression would be C=45+25h=m. Hope this helped :)

User Fkoessler
by
8.0k points
2 votes

Answer:

C = 45 + 25(h-1) + m

Explanation:

Note: All options are incorrect.

From the given information it is clear that

Fixed cost = $45

Hourly charges after the first hour = $25

Total number of hours = h

Remaining hours after first hour = (h-1)

Materials (m) for the job are an additional cost.

Total cost = Fixed cost + Hourly charges + Additional cost

C = 45 + 25(h-1) + m

Hence, the cost (C) to the customer if the job takes a total of h hours is C = 45 + 25(h-1) + m.

User PsychoDUCK
by
7.6k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories