Answer:
E. None of the above
Step-by-step explanation:
cost-to-cost method: based on the expected and incurred cost during the period we will determinate the amount of revenue recognize for the period:
expected cost: 180,000,000
incurred cost during 2017: 72,000,000
percentage of completion: 72,000,000/180,000,000 = 40%
revenue recognition: 40% of the contract:
240,000,000 x 40% = 96,000,000