Which of the following is NOT a valid principle of bottleneck​ management?

A. Increasing the capacity of a​ non-bottleneck station increases the capacity for the whole system.
B. Release work orders to the system at the pace set by the​ bottleneck's capacity.
C. Lost time at the bottleneck represents lost capacity for the whole system.
D. Increasing the capacity of a​ non-bottleneck station is a mirage.

User Faraz
by
5.1k points

1 Answer

5 votes

Answer:

A. Increasing the capacity of a non-bottleneck station increases the ability of the whole system.

Step-by-step explanation:

The bottleneck standard, or a bottleneck, happens when an arrangement of generation, for example, office, machine, or gear, is overpowered by creation to the degree that it can't satisfy needs for more production.

In the cutting edge consistently evolving markets, each time the relative parity in the generation framework is upset, you should survey the work process to check whether any new blockages happened and what should be done to decrease their impact.