Answer:
D.$400 over allocated
Step-by-step explanation:
For computing the over-allocated or under-allocated amount, first, we have to determine the predetermined overhead rate which is shown below:
Predetermined overhead rate = (Total estimated manufacturing overhead) ÷ (estimated direct labor-hours)
= $371,000 ÷ 180,000 hours
= $2.06
Now we have to find the actual overhead which equals to
= Actual direct labor-hours × predetermined overhead rate
= 190,000 hours × $2.06
= $391,400
So, the ending overhead equals to
= Actual manufacturing overhead - actual overhead
= $391,000 - $391,400
= $400 over - applied