he following information is provided for crashing analysis. Task NT CT Normal cost Crash cost Imm. Pred. A 8 6 1400 1600 -- B 5 5 500 500 -- C 3 2 800 850 A D 4 3 1100 1300 B E 6 5 900 1150 C,D The project will take days to complete. In what order would you crash the activities to crash the project by 3 days? What is the additional cost to do this crashing? 400 After crashing, the project will be completed in days. Answer 1: Correct! 17 Answer 2: Correct Answer CAE You Answered CAA Answer 3: Correct! 400 Answer 4: Correct! 14