Answer:
correct option is a. 14
Step-by-step explanation:
given data
Beginning inventory = 56 units
Forecast Weekly demand = 20 units
Period 1 orders (P1) = 24 units
Period 2 orders (P2) = 18 units
Period 3 orders (P3) = 15 units
solution
we find here Quantity before receipt of MPS in week 3 is calculated here as
Required Quantity = Beginning inventory - Order fulfill till end of period 2 ............................1
so here
Orders fulfilled till end period 2 = Period 1 + Period 2
Orders fulfilled till end period = 24 + 18
Orders fulfilled till end period = 42 units
so from equation 1
required quantity before week 3 is
Required Quantity = 56 - 42
Required Quantity = 14 units
so correct option is a. 14