Answer:
Hey there!
For what I understood, you just need to clear some points of the problem and then you can continue by your own so I gonna help you with that. Good luck!
Step-by-step explanation:
1.
a= $1,700,000 Incurred costs
b= $3,300,000 Estimated costs to complete the project
a+b= $5,000,000 Total cost of the project
2.
$1,700,000/$5,000,000 = 34% is the degree of progress of the project
3.
a-$7,000,000 Amount of contract
b-$5,000,000 Total cost of project
a-b=$2,000,000 Project profit