Answer: The total job cost for this job is: $74 600.
Explanation: The total job cost for this job is given by the sum of Direct materials, Direct labor, and overhead, so we only have to calculate overhead:
Direct materials = $13 500.
Direct labor = $23 500.
Overhead = $23500 x (1,60) = $37 600.
$13500 + $23 500 + $37 600 = $74 600.